Will your company become a critical entity?
Answer five questions. The check compares your answers with the conditions in the Polish Crisis Management Act as amended to implement the CER Directive, and works out your deadlines if you have already been entered.
Updated:
Out of scope
The critical entity rules do not apply to you
The rules on critical infrastructure operators' duties and on critical entities do not apply to bodies and units subordinate to or supervised by the Minister of National Defence (art. 1(2)(1) of the Act).
Out of scope
The critical entity rules do not apply to you
The rules on essential services and on the tasks and duties of critical entities do not apply to bodies that, within their activity, conduct preparatory proceedings under art. 297 of the Code of Criminal Procedure (art. 1(2)(2) of the Act).
This exclusion does not cover the duties of a critical infrastructure operator. If your asset is in the critical infrastructure list, those duties still apply to you.
Critical entity
You are a critical entity
A critical entity is a critical infrastructure operator entered in the list of critical entities (art. 3(1a) of the Act). The authority informs the entity of its entry within 30 days (art. 6zr(3)).
Your deadlines run from the day you received that notice. Enter the date below and we will work them out.
Probably not
Your sector is not in the annex to the Act
Only an operator working in a sector or subsector listed in the annex can become a critical entity (art. 6zp(1)(1) of the Act). The annex is broad and also covers waste, postal services and chemicals, so check the list once more.
Outside the annex you can still be a critical supplier: a company whose products, services or technologies could, if disrupted, cause a significant incident at a critical entity (art. 3(1b)). Your customer may then ask you for evidence of your own security.
Probably not in Poland
The Polish Act requires infrastructure in Poland
The Polish list covers operators with critical infrastructure in Poland or in Polish sea areas (art. 6zp(1)(3) of the Act). If you operate in another EU country, check how that country implemented the CER Directive.
Probably yes
You will most likely be entered in the list of critical entities
You are a critical infrastructure operator in an annex sector, you provide an essential service, and a disruption would be serious. These are the four conditions for entry in art. 6zp(1) of the Act.
Before the entry, the authority for your sector will ask you for information for a preliminary assessment and give you at least 14 days to reply (art. 6zq). The authorities must complete the first list by 4 April 2027 (art. 34 of the amending act).
Possibly
The list of essential services and the thresholds will decide
You meet some of the conditions in art. 6zp(1) of the Act and are unsure about others. If an authority has asked you for information (art. 6t(3), art. 6zq(1)), your company is being assessed right now: reply within the deadline you were given.
Remember that only a critical infrastructure operator can become a critical entity (art. 3(1a)). The authorities must complete the first list by 4 April 2027 (art. 34 of the amending act).
Probably not
You will not become a critical entity for now
Only a critical infrastructure operator that provides an essential service is entered in the list of critical entities (art. 3(1a), art. 6zp(1) of the Act). You become an operator when an asset is entered in the classified critical infrastructure list. Entries are requested by ministers, voivodes, the Financial Supervision Authority and the central bank (art. 6s(1)), so the list can change.
If you already are a critical infrastructure operator, your operator duties apply whatever this result says. You may also be a critical supplier to a critical entity (art. 3(1b)).
The previous single critical infrastructure list stays in force until the new list under art. 6r of the Act is drawn up (art. 31(1) of the amending act). Until your asset is entered in the new list, you protect it under the previous art. 6 of the Act (art. 32(1)), so the new deadlines for critical infrastructure operators do not run yet. The Act does not say expressly whether an owner of an asset in the old list already counts as an operator for art. 6zp, so the result is conditional.
The list of essential services and the significance thresholds will be set by a regulation of the Council of Ministers (art. 6zp(3) of the Act), and without the thresholds the authorities cannot assess the significance of a disruption (art. 6zp(2)). The draft regulation (RC21) is being prepared by the Director of the Government Centre for Security. The government work list planned its adoption in the third quarter of 2026; by 29 October 2026 it had not been adopted. That is why the result is an estimate. Draft regulation on the Council of Ministers website (in Polish)
Your deadlines as a critical entity
Counted from the day you received the notice of entry in the list of critical entities.
Banking and financial market infrastructure have 10 months for the risk assessment (art. 6zze) and apply only part of chapters 11–15 (art. 6zzw). Check with a lawyer which of these deadlines apply to you.
Chapters 11–15 of the Act do not apply to critical entities in digital infrastructure (art. 6zzx), so these deadlines do not apply to you. Check your cybersecurity duties under the Polish National Cybersecurity System Act.
Pick a date and the deadlines appear below.
Entries under the new rules are possible from 4 July 2026. An earlier notice concerns the previous list, and the new deadlines do not run for it yet.
You report a significant incident within 24 hours of its occurrence or detection and send a report within 30 days (art. 6zv(1)(4) and (7)). You repeat the risk assessment at least every 2 years (art. 6zt(1)(1)).
The dates are indicative. A term in months ends on the day with the same number, or on the last day of the month if that day does not exist. Implementation is counted from the last day allowed for the analysis or assessment; finish it sooner and implementation is due sooner too.
Your deadlines as a critical infrastructure operator
Counted from the day you received the notice of entry in the critical infrastructure list.
Pick a date and the deadlines appear below.
Entries under the new rules are possible from 4 July 2026. An earlier notice concerns the previous list, and the new deadlines do not run for it yet.
The dates are indicative. A term in months ends on the day with the same number, or on the last day of the month if that day does not exist. Implementation is counted from the last day allowed for the analysis or assessment; finish it sooner and implementation is due sooner too.
What about drones?
The Act does not mention drones. A critical entity must, however, include antagonistic threats in its risk assessment and physical protection of buildings and grounds in its measures (art. 6zt(1)(1)(a) and (2)(b) of the Act). A critical infrastructure operator runs an ongoing threat analysis and puts physical security in place (art. 6ze(1)(1) and (2)(a)).
That analysis needs data: how many Remote ID drones fly over the site, when, and where they take off. A 90-day HARQ trial records exactly that and ends with a flight report.
How it works
Poland implemented the CER Directive with the act of 29 May 2026, which amended the Crisis Management Act and has applied since 4 July 2026. Entry in the list of critical entities takes two steps. First an asset is entered in the classified critical infrastructure list, and its owner or holder becomes a critical infrastructure operator (art. 3(3a), art. 6r). Then the operator is entered in the list of critical entities if it meets all four conditions (art. 6zp(1)):
- it works in a sector or subsector listed in the annex to the Act,
- it provides at least one essential service,
- it has critical infrastructure in Poland or in Polish sea areas,
- an incident would have a significant disruptive effect on the provision of that service.
The check asks about the same things. It does not know the list of essential services or the significance thresholds, because the Council of Ministers has not yet adopted the regulation that will set them (draft RC21). That is why the result is indicative.
Frequently asked questions
Who decides on entry in the list of critical entities?
The critical entity authority for the sector, for example a minister or the Financial Supervision Authority. It first asks the operator for information (art. 6zq), then files a request for entry, and the entry is made automatically in the IT system. The operator is informed within 30 days (art. 6zr(1)–(3) of the Act).
How do I know whether I am a critical infrastructure operator?
The Director of the Government Centre for Security informs the owner or holder of an asset of its entry in the critical infrastructure list, and of the duties that follow, within 30 days of the entry (art. 6w(1) of the Act). The list itself is classified (art. 6r(3)).
When will the first list of critical entities be ready?
The authorities must identify the first critical entities and enter them within 9 months of the amending act entering into force (art. 34), that is by 4 April 2027. The act has applied since 4 July 2026 (art. 73).
How long does a critical entity have for the risk assessment?
9 months from the notice of entry (art. 6zt(3) of the Act), 10 months in banking and financial market infrastructure (art. 6zze). Organisational and technical measures follow within 3 months of the assessment (art. 6zt(4)), and the documentation within 15 months of the notice (art. 6zu(4)).
Does the check store my answers?
No. It runs in your browser and sends neither your answers nor the date to any server.
Sources
Law as of 29 October 2026. We checked the provisions in ISAP and the ELI API of the Chancellery of the Sejm, in the consolidated text of the Act and in the amending act as published.
- Crisis Management Act of 26 April 2007 (ustawa o zarządzaniu kryzysowym), consolidated text Dz.U. 2026 item 574 as amended
- Act of 29 May 2026 amending the Crisis Management Act and certain other acts (Dz.U. 2026 item 815): art. 1 (art. 1(2)(1) and (2), art. 3(1a), (1b), (1e) and (3a), art. 6r, 6s, 6t, 6w, 6ze, 6zf, 6zi, 6zp, 6zq, 6zr, 6zt, 6zu, 6zv, 6zzd, 6zze, 6zzw, 6zzx and the annex of the Act), art. 31, art. 32, art. 34, art. 73
- Draft regulation of the Council of Ministers on the list of essential services and the significance thresholds (RC21), Council of Ministers website, as of 29 October 2026 (in Polish)
- Directive (EU) 2022/2557 of the European Parliament and of the Council of 14 December 2022 on the resilience of critical entities
This check is for information only and is not legal advice. The authorities decide on entries using information the check does not have. For your specific case, consult a lawyer.